Skip to content
ELO

Power & Energy

Power is the bottleneck. We source it.

AI data centers are built or stalled by one thing: access to firm, deliverable power. ELO Advisors originates the deals that get projects energized, from power contracts and behind-the-meter generation to capacity and grid access, sourced off-market and structured to move.

01 / The Bottleneck

Land is the easy part. Power is the hard one.

A site without power is a field. The grid cannot keep up: new connections take years, and the generation and equipment behind them take longer. Power now decides when, where, and whether a data center gets built.

Time to connect

~5 years

Typical wait to connect a new project to the US grid, up from under two years in 2008.

Source: Berkeley Lab, 2025.

02 / The Market

Demand is doubling. Supply is years behind.

Data-center power demand is set to more than double by 2030, while the grid, the turbines, and the transformers all run on multi-year lead times.

~9%

Of US electricity used by data centers by 2030, up from about 4 percent today

EPRI / LBNL

~2.2TW

Of generation waiting in US grid interconnection queues

Berkeley Lab

~80GW

Gas-turbine backlog, with delivery slots now sold into 2030

GE Vernova

11x

Jump in PJM grid-capacity prices in a single auction, blamed on data-center load

PJM

How fast can you get power?

Sources: EPRI, 2026; Berkeley Lab, 2025; GE Vernova, 2025; PJM / IEEFA, 2025; IEA, 2025.

03 / How We Source Power

Every path to firm power, in one place.

We originate across the structures that actually get a data center energized.

01

Power purchase agreements

Long-term offtake contracts with generators, the backbone of large power deals.

02

Behind-the-meter generation

On-site gas and dedicated generation that bypasses the grid queue and runs in months.

03

Capacity & grid rights

Interconnection positions and capacity-rights transfers, the genuinely scarce assets.

04

Nuclear & IPP offtake

Output from restarts, independent power producers, and new generation, contracted direct.

05

Utility & tariff deals

Negotiated arrangements, often where the developer funds the grid upgrades it triggers.

06

Fuel supply

Gas supply agreements and the contracts that keep on-site generation running.

04 / Speed to Power

Months, not years.

The grid queue is five years. We find the power that moves now: behind-the-meter, stranded capacity, and offtake that is already available.

  1. 01

    We map the load and the timeline

    How much power, where, by when, and what the project can tolerate.

  2. 02

    We source firm electrons

    PPAs, behind-the-meter, capacity rights, and IPP offtake that can actually be delivered.

  3. 03

    We structure the deal

    The contract, the terms, and a path around the five-year interconnection queue.

  4. 04

    We line up fuel and equipment

    Gas supply, turbine slots, and the long-lead gear the deal depends on.

  5. 05

    We close, and you energize

    Documented, deliverable power on a timeline that fits the build.

05 / Where We Fit

We trade in power you can actually plug in.

Anyone can announce a gigawatt. The scarce thing is power that is contracted, deliverable, and on a real timeline. That is what we source, and what we will not overstate.

Deliverable, not announced

In a market full of press releases, we source power that is contracted and real.

Off-market

Capacity, offtake, and interconnection positions move through relationships, not listings.

Speed over size

We find the megawatts that can energize a build now, not the ones stuck in a queue.

06 / Our Network

We sit between the grid and the build.

Demand

  • Data-center developers
  • Hyperscalers and neoclouds
  • EPCs and site operators
  • Industrial large loads

Supply

  • Independent power producers
  • Utilities and grid operators
  • Gas suppliers and generators
  • Turbine and equipment makers

07 / Questions

What kind of power do you source?

Grid PPAs, behind-the-meter generation, capacity and interconnection rights, and offtake from IPPs and nuclear. Whatever gets the site energized.

How fast is behind-the-meter?

On-site gas can be running in roughly 18 months, against five years or more for a new grid connection. It is the main bridge while the grid catches up.

Do you work with generators too?

Yes. If you have power, capacity, or an interconnection position to place, we have the demand side asking for it.

How are you paid?

A success fee on the deal, with a work fee for live mandates. The structure keeps us aligned with getting power under contract.

08 / Contact

Need power for a site, or power to place?

Tell us the load, the location, and the timeline, or the generation you have. We will tell you how we would source or place it.